CouncilNow

The giants lurking under our suburban streets

Storm water pipes with manholes up to 2.7 metres in diameter are the giants beneath streets which help reduce flash flooding during heavy rainfall.

Without them life in many suburban streets would be chaotic during thunderstorms and prolonged wet weather.

Goondoola Street Redbank Plains is only one example of hidden infrastructure that keeps city streets safe during severe weather.

During the months of October 2018 to January 2019 the drainage system was replaced as it had reached the end of its life.

Ipswich City Council Infrastructure Services chief Charlie Dill said this pipe replacement was larger and deeper and more challenging than our usual replacement of storm water drainage.

“While most road reconstruction jobs requires some form of pipework seldom was it seen to this extent.

“This job had 12 pits in total with one of the manholes being 2.4m diameter.

“They ranged in depth from 1.7m to 2.7m to invert (bottom side of the pipe), and required about 225m of underground pipes at the same depth.

“Generally the depth of drainage is about 1.5m.”

He said adding to the job was the 14 tonne precast concrete pump well structure that had to go in the middle of the road and be manoeuvred into place over the top of an existing system.

“A 14 tonne crane lift over other pipes was more challenging than would normally be expected”, Charlie Dill said.

“We also had a week where rain made it unsafe to continue with the deep drainage works. Which extended the scheduled 10 weeks.

“Difficult ground conditions meant the crews had to modify their work methods, which resulted in the road being closed for the remainder of project to ensure safety was the priority.”

As well as the stormwater drainage reconstruction, rehabilitation works to the kerb and channel and road pavement on Goondoola Street were completed.

“On behalf of our crews I’d like to thank residents for their patience during the construction period.”

Back to top button
X
X