Hunter Street roadworks resume

Roadworks in progress on Hunter Street Brassall Tuesday January 8, 2019

Hunter Street roadworks on track for March 2019 completion

Work resumed this week on the rehabilitation of Hunter Street Brassall between Pine Mountain Road and Rowan Drive.

All service relocations were completed prior to Christmas.

Night works were also carried out before Christmas to enable construction under appropriate safety measures.

Day works are now in place until mid-February 2019 with the final works to take place at night in late February and early March.

When completed, the $3.5m project between Pine Mountain Road and Rowan Drive will feature:

* New road resurfacing from kerb to kerb, including sections of full pavement replacement

* Sections of kerb and channel replaced including some driveways and footpaths

* Line marking

* New tree plantings

If you have any questions or concerns during this project contact council by phone or email.

* Phone: 07 3810 6666 during office hours (8am to 4.30pm)

* Email: [email protected]

IPSWICH FIRST THREE TIMES A WEEK TO YOUR INBOX

One Comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button
X
X